Constructing a 1 Kanal house in Lahore is a milestone for many homeowners, offering both space and luxury. From the sturdy grey structure to fine interior finishes, every phase requires careful budgeting, professional guidance, and premium materials. Here, we provide a detailed breakdown of the cost, materials, and scope for building a fully finished 1 Kanal house in Lahore.
1 Kanal House Area Details
Total Covered Area: Approximately 5,950 sq ft
Ground Floor: 3,000 sq ft
First Floor: 2,700 sq ft
Mumty: 250 sq ft
Standard Layout:
5–6 Bedrooms with attached bathrooms
Kitchens and lounges on both floors
Drawing/Dining Room
Garage, Lawn & Servant Quarters
Grey Structure Construction Cost (Approx. Rs. 7,500,000)
Major Material Quantities and Costs:
Material | Quantity / Details | Cost (PKR) |
---|---|---|
Bricks | 135,000 @ Rs 15 | 2,025,000 |
Sand | Chenab (2,100 cu ft) | 105,000 |
Ravi (5,250 cu ft) | 73,500 | |
Gravel | Margalla (2,200 cu ft) | 154,000 |
Sargodha (1,200 cu ft) | 78,000 | |
Kassu | – | 200,000 |
Cement | 1,600 bags @ Rs 550 | 880,000 |
Steel | 9 tons @ Rs 125/kg | 1,125,000 |
Additional Structural Work:
Work | Cost (PKR) |
---|---|
Plumbing | 200,000 |
Electrical Wiring | 285,000 |
Main Gate | 150,000 |
Grills | 175,000 |
Termite Spray | 55,000 |
Bitumen + Membrane | 57,000 |
Labour Cost:
Rs 450/sq ft × 5,950 sq ft = Rs 2,796,500
Finishing Costs (Approx. Rs. 7,800,000)
Flooring and Tiles:
Work | Cost (PKR) |
---|---|
Floor Tiles | 1,953,000 |
Bath Tiles | 630,000 |
Terrace Tiles | 157,500 |
Marble (Stairs & Dales) | 277,500 |
Doors, Windows & Woodwork:
Item | Estimated Cost (PKR) |
---|---|
Wooden Doors | 1,100,000 |
Wardrobes | 850,000 |
Kitchen Cabinets | 450,000 |
Window Aluminum | 300,000 |
Handles & Locks | 120,000 |
Ceiling, Paint & Accessories:
Item | Estimated Cost (PKR) |
---|---|
False Ceiling | 350,000 |
Interior & Exterior Paint | 750,000 |
Lights & Fixtures | 550,000 |
Bathroom Accessories | 350,000 |
Geysers & Fans | 300,000 |
Total Estimated Construction Cost:
Phase | Estimated Cost (PKR) |
---|---|
Grey Structure | 7,500,000 |
Finishing | 7,800,000 |
Total | 15,300,000 |
Note: These costs are estimates based on current market rates in Lahore and may vary depending on location, design complexity, and material preferences.
Why Choose ACCO Construction?
✅ Over 15 Years of Experience
✅ Turnkey House Construction Services
✅ Transparent Cost Estimations
✅ Premium Materials and Finishing
✅ Free Consultation & Custom Design Options
Start Your Dream Project Today!
📍 Visit: www.acco.com.pk
📧 Email: info@acco.com.pk
📞 Call/WhatsApp: 0322 8000190
Building Your Dream House in Lahore: Updated 1 Kanal House Construction Cost
📞 Contact Us:
🌐 www.acco.com.pk
✉️ info@acco.com.pk
📱 0322 8000190
Overview
Constructing your dream home in Lahore is an exciting journey that involves careful planning and a clear understanding of costs—from the essential grey structure to the final luxurious finishes. At ACCO Construction, we provide transparent, updated rates to help you budget accurately while ensuring quality workmanship and premium materials.
In this updated cost breakdown, we’ve incorporated revised rates for materials and labor to reflect current market trends.
1 Kanal House – Area & Layout
Total Covered Area: Approximately 5,950 sq ft
Ground Floor: 3,000 sq ft
First Floor: 2,700 sq ft
Mumty (Loft): 250 sq ft
A standard 1 Kanal house is designed for spacious living with 5–6 bedrooms (each with attached bathrooms), kitchens and lounges on each floor, plus additional spaces like a lawn, garage, or servant quarters.
Updated Grey Structure Construction Cost
The grey structure forms the backbone of your home and includes the foundation, walls, roof, and basic infrastructure. Our updated calculations are as follows:
Major Material Costs
Material/Work | Quantity/Details | Updated Rate | Cost (PKR) |
---|---|---|---|
Bricks | 135,000 bricks @ Rs. 18 each | Rs. 18 per brick | 2,430,000 |
Sand | Option: Ravi Sand – 5,250 cu ft | Rs. 88,200 total (for 5,250 cu ft) | 88,200 |
Gravel | Margalla (roof/lintel) 2,200 cu ft | Rs. 184,800 (Margalla) | 184,800 |
Sargodha (floor) 1,200 cu ft | Rs. 93,600 (Sargodha) | 93,600 | |
Kassu | – | Updated to Rs. 240,000 | 240,000 |
Cement | 1,600 bags @ Rs. 660 per bag | Rs. 660 per bag | 1,056,000 |
Steel | 9 tons (9,000 kg) @ Rs. 150 per kg | Rs. 150 per kg | 1,350,000 |
Additional Structural & Utility Work
Item | Updated Rate/Cost (PKR) |
---|---|
Electrical Wiring | Updated range: Rs. 285,000–330,000 (average: ~307,500) |
Plumbing Work | Rs. 240,000 |
Main Gate | Rs. 180,000 |
Grills & Installation | Rs. 210,000 |
Termite Spray | Rs. 60,000 |
Waterproofing Materials | Approximately Rs. 68,400 |
Labour Cost
Labour: Updated to Rs. 500 per sq ft
Total Labour for 5,950 sq ft:
5,950 × Rs. 500 = 2,975,000
Grey Structure Total
Let’s sum the key items:
Bricks: 2,430,000
Sand: 88,200
Gravel (combined): 184,800 + 93,600 = 278,400
Kassu: 240,000
Cement: 1,056,000
Steel: 1,350,000
Electrical: ~307,500
Plumbing: 240,000
Main Gate: 180,000
Grills: 210,000
Termite Spray: 60,000
Waterproofing: 68,400
Labour: 2,975,000
Total Grey Structure Cost:
≈ 9,483,500 PKR
Updated Finishing Construction Cost
Finishing transforms the grey structure into a comfortable, luxurious home. The updated finishing rates reflect a 20% increase over previous estimates.
Finishing Components
Flooring & Tiling
Item | Updated Cost (PKR) |
---|---|
Floor Tiles | Previously Rs. 1,953,000 → Rs. 2,343,600 |
Bath Tiles | Rs. 630,000 → Rs. 756,000 |
Terrace Tiles | Rs. 157,500 → Rs. 189,000 |
Marble (Stairs, Dales) | Rs. 277,500 → Rs. 333,000 |
Subtotal (Tiles & Marble): ≈ 3,621,600 PKR
Doors, Windows & Woodwork
Item | Updated Cost (PKR) |
---|---|
Wooden Doors | Rs. 1,100,000 → Rs. 1,320,000 |
Wardrobes | Rs. 850,000 → Rs. 1,020,000 |
Kitchen Cabinets | Rs. 450,000 → Rs. 540,000 |
Window Frames (Aluminum) | Rs. 300,000 → Rs. 360,000 |
Handles & Locks | Rs. 120,000 → Rs. 144,000 |
Subtotal (Woodwork): ≈ 3,384,000 PKR
Ceiling, Paint & Accessories
Item | Updated Cost (PKR) |
---|---|
False Ceiling | Rs. 350,000 → Rs. 420,000 |
Interior & Exterior Paint | Rs. 750,000 → Rs. 900,000 |
Lights & Fixtures | Rs. 550,000 → Rs. 660,000 |
Bathroom Accessories | Rs. 350,000 → Rs. 420,000 |
Geysers & Fans | Rs. 300,000 → Rs. 360,000 |
Subtotal (Ceiling, Paint & Accessories): ≈ 2,760,000 PKR
Finishing Total
Total Finishing Cost:
3,621,600 + 3,384,000 + 2,760,000 ≈ 9,765,600 PKR
Overall Updated Total Construction Cost
Phase | Cost (PKR) |
---|---|
Grey Structure | ≈ 9,483,500 |
Finishing Works | ≈ 9,765,600 |
Total Estimate | ≈ 19,249,100 PKR |
Note: These updated rates are based on current market trends and may vary slightly based on design changes, material selections, and site-specific conditions.
Additional Considerations
Optional Add-Ons: Smart home automation, solar panels, home theatre, basement, and advanced security systems can be included at additional cost.
Design & Customization: Our expert team ensures that every aspect of the construction—from the initial blueprint to the final finishing—reflects your personal taste and lifestyle.
Why Choose ACCO Construction?
Over 15 years of trusted industry experience
Comprehensive turnkey solutions
Transparent, updated cost estimates
In-house design and engineering expertise
Commitment to quality, safety, and timely delivery
Get Started on Your Dream Home
For a free consultation or a customized quote, contact ACCO Construction today. Let us help you transform your vision into reality.
📞 Call/WhatsApp: 0322 8000190
✉️ Email: info@acco.com.pk
🌐 Visit: www.acco.com.pk