4 Marla Commercial Plaza Construction Cost in DHA – Grey Structure & Finishing Rates (2025)

4 Marla Commercial Plaza Construction Cost – Grey Structure & Finishing Breakdown
🏢 4 Marla Commercial Plaza Construction Cost – Grey Structure & Finishing Breakdown
Published by ACCO Construction – Your Trusted DHA Builders
www.acco.com.pk | info@acco.com.pk | +92 322 8000190
Are you planning to invest in a 4 Marla commercial plaza in DHA Lahore and want to understand the complete construction cost, from grey structure to finishing? You’ve landed at the right place! At ACCO Construction, we specialize in designing and constructing commercial plazas with modern architecture, top-tier materials, and precise cost control—giving our clients the best value for money.
📌 Overview: Why Choose a 4 Marla Commercial Plaza?
In DHA Lahore, a 4 Marla commercial plot typically measures 30 ft × 30 ft with 4 to 5 floors (Ground + Mezzanine + 2-3 Floors) allowed, depending on DHA regulations.
🔑 Key Features:
Prime Commercial Location in DHA
Ideal for: Offices, Brands, Clinics, Cafés
High ROI due to rental demand
DHA Approval ensures security & legality
📏 📐 Covered Area Calculation
Floor | Dimensions | Area (sq. ft.) |
---|---|---|
Ground Floor | 30 × 30 | 900 |
Mezzanine Floor | 30 × 15 | 450 |
First Floor | 30 × 30 | 900 |
Second Floor | 30 × 30 | 900 |
Third Floor | 30 × 30 (optional) | 900 |
Total Area | — | 5,625 sft |
💸 Total Construction Cost (2025 Updated) | Per SFT Breakdown
Note: Rates are updated for 2025 with 20% market inflation included.
Component | Rate (PKR/sft) | Total (PKR) |
---|---|---|
Grey Structure | 4,080 | 22,950,000 |
Finishing Works | 3,000 | 16,875,000 |
MEP (Mechanical, Electrical, Plumbing) | 720 | 4,050,000 |
Elevation / Facade | 960 | 5,400,000 |
DHA Approval & Utilities | Fixed | 1,200,000 |
Total Cost | 8,760/sft | 50,475,000 PKR |
✅ Total Covered Area: 5,625 sft
✅ Per SFT Cost: PKR 8,760/sft
🔨 Grey Structure Cost Details (PKR 4,080/sft)
The grey structure is the foundation of your plaza. It includes:
🚧 Civil Works
Excavation & Backfilling
PCC, RCC Works
Brick Masonry
Lintels, Beams, Slabs
🧱 Material Cost Includes:
Margalla Crush
Sand (Lawrencepur / Ravi)
Bricks (A+ Quality)
Cement (Maple Leaf, DG Khan)
Steel (60 Grade)
📦 Labor & Miscellaneous:
Skilled & unskilled labor
Scaffolding, shuttering
Safety & site logistics
👉 Grey Structure Cost = 5,625 × 4,080 = PKR 22,950,000
🎨 Finishing Cost Details (PKR 3,000/sft)
The finishing phase is what makes your plaza appealing to tenants and customers.
🪟 Flooring
Porcelain tiles (24×24 or 18×18)
Granite for staircases & lobby
🚪 Wood & Metal Works
Main doors, aluminum windows
Toughened glass shopfronts
💡 Electrical & Fixtures
Wiring, distribution boxes
LED lights, fans, switches (ABB, Schneider)
🛁 Bathrooms
Porta / Sonex / Marachi fittings
Tiles, vanity, exhaust system
👉 Finishing Cost = 5,625 × 3,000 = PKR 16,875,000
⚡ MEP Works (PKR 720/sft)
💧 Plumbing
Water supply, drainage
Pumps, water tanks
🔌 Electrical
DB Panels, wiring
Conduits, backup generator wiring
❄️ HVAC (Optional)
Provision for Split / VRF Units
👉 MEP Cost = 5,625 × 720 = PKR 4,050,000
🧱 Elevation / Front Facade (PKR 960/sft)
A premium commercial façade includes:
ACP Sheets / Curtain Walls
Glass Panels with Aluminum Frame
Exterior Paint or Texture
Signage Frames & Branding Provisions
👉 Elevation Cost = 5,625 × 960 = PKR 5,400,000
📑 DHA Approvals & Utilities (Fixed Cost)
Required NOCs:
DHA Building Plan Approval
WASA & Electricity Connections
SNGPL (Optional for food outlets)
👉 Cost = PKR 1,200,000 (lump sum)
📊 Summary Table – Total Cost Breakdown
Item | Rate (PKR/sft) | Total Cost (PKR) |
---|---|---|
Grey Structure | 4,080 | 22,950,000 |
Finishing Work | 3,000 | 16,875,000 |
MEP Works | 720 | 4,050,000 |
Elevation / Façade | 960 | 5,400,000 |
DHA Approvals + Utilities | Fixed | 1,200,000 |
Grand Total | 8,760/sft | PKR 50,475,000 |
🔍 FAQs – 4 Marla Commercial Plaza Construction in DHA
❓ What is the construction timeline?
Typically, 10–12 months including approvals, grey structure, and finishing.
❓ Do you provide design & approvals?
✅ Yes! ACCO Construction offers complete design + DHA approval + execution services.
❓ Can I customize materials and finishes?
Absolutely! We offer flexible packages (Basic, Premium, Smart) tailored to your budget.
🏗️ Why Choose ACCO Construction?
✅ Over 20 Years of Experience
Serving Lahore, Islamabad, Karachi, and Multan.
✅ End-to-End Turnkey Services
From architecture to final key handover.
✅ DHA Compliance Experts
All our designs and builds are DHA-compliant and approved.
✅ International Quality Standards
We follow ISO-certified processes and modern construction techniques.
🌐 Visit: www.acco.com.pk
📞 Call: +92 322 8000190
📧 Email: info@acco.com.pk
🔗 Internal Links (On Your Website)
🌐 External Useful Links
📣 Final Words: Build Smart, Build with ACCO
Your 4 Marla Commercial Plaza in DHA Lahore deserves premium quality, professional execution, and on-time delivery. At ACCO Construction, we don’t just build structures—we build legacies.
Whether you’re an investor, a business owner, or a brand expanding in DHA Lahore, we are ready to build your commercial success from the ground up.
📞 Contact ACCO Construction today for a free consultation or quotation.
4 Marla Commercial plaza construction cost
Previously, all articles on the cost by Team ACCO applied to residential construction projects only, however, there was a very popular demand by our followers for commercial plaza construction cost frame structure. Since Team ACCO already has a first-hand experience of various commercial projects completed in Lahore & Islamabad, hence it is easy for us to guide our followers about the cost of a commercial plaza built as a frame structure. However, most of the methods of calculating cost might be the same as in our previous articles and videos, there is one significant change in this video where we have also mentioned quantities along with the per sqft costs. Similarly, like previous residential costing videos, this costing video for the commercial plaza will also be only for the grey structure.
Commercial plaza construction can be done by two methods which should be known before going towards the construction cost of a commercial plaza:
Labour contract
A contract in which the owner procures material and supervises labor on a self-help basis. A labor contractor is responsible for arranging required labor to carry out construction procedures. Construction cost, in this case, is all in hands of the owner himself. The final cost of construction will depend upon how well the owner has managed the construction process both in regards to material procurement and labor procurement. In this video, we will discuss the construction cost of this method.
Turnkey contract
This is a method or contract in which the owner hires a professional company on a lump sum or per square foot construction rate for a turnkey solution. The owner does not have to worry about the construction cost as the builder has agreed to provide him with all services within in predefined budget and cost. The owner only must supervise if a builder is carrying out the work as per the agreement or not. At the end of this video, we will tell you how much a professional company charges for its services and how much per square foot you will have to pay extra than the cost that could have been if you build the commercial plaza yourself.
Sample project
4 Marla commercial plaza construction cost (125 sq. Yd)
Covered area TOTAL 4900 sq. Ft including
- Basement 1200 sqft
- Ground floor 1200 sqft
- first floor 1200 sqft
- Second floor 1200 sqft
- Mumtee 100 sqft
Item wise per square foot commercial plaza construction cost:
Bricks 125 Rs/sq. Ft
Calculation:
125 Rs x 4900 sq. Ft=612500 Rs
Brick price =11.5 Rs per piece
Quantity =612500/11.5 = 53260 bricks
Crush 131 Rs/sq. Ft
Calculation:
131 Rs x 4900 sq. Ft=641900 Rs
Crush price =80 Rs per Cft
Quantity =641900/80 = 8024 Cft
Cement 175 Rs/sq. Ft
Calculation:
175 Rs x 4900 sq. Ft=857500 Rs
Cement price =500 Rs/50kg bag
Quantity =857500/500 = 1715 bags
Steel 620 Rs/sq. Ft
Calculation:
620 Rs x 4900 sq. Ft=3038000 Rs
Steel price =111 Rs/kg or 111000 Rs/ton
Quantity =3038000/111 = 27370 kg or 27.37 tons
Sand 50 Rs/sq. Ft
Calculation:
50 Rs x 4900 sq. Ft=245000 Rs
Sand price =30 Rs/Cft
Quantity =245000/30 = 8166 Cft
Labour contractor 450 Rs/sq. Ft
Calculation:
450 Rs x 4900 sq. Ft = 2205000 Rs
Steel fixer 36 Rs/sq. Ft
Calculation:
36 Rs x 4900 sq. Ft = 176400 Rs
Plumbing contractor 18 Rs/sq. Ft
Calculation:
18 Rs x 4900 sq. Ft = 88200 Rs
Electric contractor 18 Rs/sq. Ft
Calculation:
18 Rs x 4900 sq. Ft = 88200 Rs
POINT TO BE NOTED:
The Labour rate considered as 450 in this calculation includes each thing related to labor & machinery such as masons, helpers, mixing machines, vibrators, scaffolding, and shuttering. Since this method of construction is a frame structure, shuttering has a very critical role. Best quality shuttering is done with steel plates of 4ftx8ft palai sheets. In this labor rate, we have considered the use of both steel plates and palai for shuttering columns, slabs, basement retaining walls, etc. Another critical labor is the steel fixer for which the per ton labor rate has been considered at the rate of 6500 Rs. Similarly, electrician and plumber rates include complete work related to electrical and plumbing till grey structure i-e conduit in slabs and walls, hot and cold-water pipes, drainpipes & main sewerage lines, etc
Other items
Excavation 10 Rs/sq.ft
Calculation:
10 Rs x 4900 sq.ft= 49000 Rs
Waterproofing 10 Rs/sq.ft
Calculation:
10 Rs x 4900 sq.ft= 49000 Rs
Waterproofing considered in this method is the simple chemical coating of Ultra of Sika any of the brand surface area rate of which is maximum up to 20 rs/sqft. For a stronger water proofing method for basement retaining walls PVC membrane sheets can be used however it will add up to the overall waterproofing cost because it is expensive.
Water stopper 5 Rs/sq.ft
Calculation:
5 Rs x 4900 sq.ft= 24500 Rs
Electricity items 35 Rs/sq.ft
Calculation:
35 Rs x 4900 sq.ft= 171500 Rs
Electric items include complete uPVC conduit (pipes) required in walls, slabs, underground, etc. It also includes complete switchboard internal box fittings required for standard Chinese fittings. Main DB (Distribution boxes) are also included in these figures for the ground and first floor. Electric conduit witnessed a sharp increase in prices in 2019/20 as compared to 2018.
Plumbing items 70 Rs/sq.ft
Calculation:
70 Rs x 4900 sq.ft= 343000 Rs
Plumbing items include complete PPRC pipes and their fittings such as elbows, bends, T’s, etc required for water and gas connections. It also includes complete uPVC piping for sewerage and drain systems. It also includes a typical and standard 400 gallons plastic overhead water tank with GI (steel) pipes fitting. Plumbing conduit witnessed a sharp increase in prices in 2019/20 as compared to 2018.
Brick Tile 15 Rs/sq.ft
Calculation:
15 Rs x 4900 sq.ft= 73500 Rs
Brick tile is required during the process of waterproofing and finishing the floor of roofs. The brick tile considered in this cost is up to 10 Rs/brick tile.
Guard Salary 16 Rs/sq.ft
Calculation:
16 Rs x 4900 sq.ft= 78400 Rs
Guard salary has been considered on basis of 15000 Rs/month for a tenure of 5 months maximum.
Gravel 20 Rs/sq.ft
Calculation:
20 Rs x 4900 sq.ft= 98000 Rs
Bitumen 5 Rs/sq.ft
Calculation:
5 Rs x 4900 sq.ft= 24500 Rs
Polythene sheet 4 Rs/sq.ft
Calculation:
4 Rs x 4900 sq.ft= 19600 Rs
Mud 4 Rs/sq.ft
Calculation:
4 Rs x 4900 sq.ft= 19600 Rs
Chips Aggregate 5 Rs/sq.ft
Calculation:
5 Rs x 4900 sq.ft= 24500 Rs
Taxes 6 Rs/sq.ft
Calculation:
6 Rs x 4900 sq.ft= 29400 Rs
Electricity bills 5 Rs/sq.ft
Calculation:
5 Rs x 4900 sq.ft= 24500 Rs
Water boring 5 Rs/sq.ft
Calculation:
5 Rs x 4900 sq.ft= 24500 Rs
Anti termite spray 7 Rs/sq.ft
Calculation:
7 Rs x 4900 sq.ft= 34300 Rs
Random expenditures 20 Rs/sq.ft
Calculation:
20 Rs x 4900 sq.ft= 98000 Rs
Let us see what will be the total cost of the Grey structure for 4 marlas commercial plaza frame structure method:
4 Marla Shopping Mall Cost | |||
S# | Item | 2020 per sqft cost | 2020 Total approximate cost |
1 | Bricks | 125 | 612500 |
2 | Crush | 131 | 641900 |
3 | Cement | 175 | 857500 |
4 | Steel | 620 | 3038000 |
5 | Sand | 50 | 245000 |
6 | Labor cont | 450 | 2205000 |
7 | Steel fixer | 36 | 127400 |
8 | Plumbing | 18 | 88200 |
9 | Electric | 18 | 88200 |
10 | Electric items | 35 | 171500 |
11 | Plumbing items | 70 | 343000 |
12 | Earthfill | 0 | 0 |
13 | Brick tile | 15 | 73500 |
14 | Guard Salary | 14 | 68600 |
15 | Gravel | 20 | 98000 |
16 | Excavation | 10 | 49000 |
17 | Bitumen | 5 | 24500 |
18 | Polythene sheet | 4 | 19600 |
19 | Mud | 4 | 19600 |
20 | Chips | 5 | 24500 |
21 | Taxes | 6 | 29400 |
22 | Electric bills | 5 | 24500 |
23 | Boring | 5 | 24500 |
24 | Anti termite | 7 | 34300 |
25 | Random | 20 | 98000 |
26 | Water proofing | 10 | 49000 |
27 | Water stopper | 5 | 24500 |
Total | 1865 | 9138500 |
Disclaimer:
-Possible ±5% Variation is possible in cost shown in video
-Rates applicable on frame structures only in Lahore & Islamabad/Rawalpindi
-Skills required to achieve this cost:
-Past construction experience
-Quality & honest labour
-Labour management skills
-Quality, timely & cost-effective material procurement
-Factors such as construction inexperience, unusual