Acco’s fast growing construction company based in Lahore, Pakistan. We undertake civil construction, interior designing & decoration and fabrication services of residential, institutional and commercial buildings throughout all over Pakistan. We are keen to carve a niche in the market by delivering high quality construction and engineering solutions within budgeted time and costs. Incepted in 1999, we develop high-end residential and commercial projects including villas, hotels, office complexes, malls etc and provide complete construction solutions. Acco has gained over 20 years of fruitful experience in civil and commercial construction industry.

icon_widget_image Monday-Friday: 9am to 9pm; Satuday: 10ap to 4pm icon_widget_image Office 24, 2nd Floor BigCity Plaza, Gulberg-III, Lahore icon_widget_image + (92) 322-8000-190 + (923) 111-749-849 icon_widget_image info@acco.com.pk ahmed@acco.com.pk

List of NOCs, Approval Required for Project in Jurisdiction of CDA: Housing Schemes

List of NOCs, Approval Required for Project in Jurisdiction of CDA: Housing Schemes

[ad_1]


Post Views:
3

The Capital Development Authority has released a comprehensive list highlighting all the approvals and No Objection Certificates (NOCs) required for the process for investing and development in Pakistan’s real estate market. 

Graana.com brings you a list of required documents for NOCs/approvals for a project in a plot of approved housing schemes. It is as follows:

  1. Ownership Documents: 
    1. Allotment Letter or Certificate 
    2. Possession Letter 
    3. Demarcation Certificate 
  2. NOC and Approved Layout Plan of Housing Scheme. 
  3. No Objection Certificate (NOC) by Authority to Process the Building Plan approvals in CDA. 
  4. Approved Layout Plan. 
  5. Approval letter of Design Vetting Committee (DVC). 
  6. Approved Building Plans Letter. 
  7. Approved Building Plans vetted by the Competent Authority. 
  8. Third-party vetting Certificates: 
    1. Structural Design Vetting Certificate 
    2. Mechanical, Electrical and Plumbing (MEP Certificate) 
    3. Firefighting Certificate 
  9. Access Road Approval (In case of CDA major avenues & Astride Roads). 
  10. Approved letter from National Highway Authority (NHA) (In case of GT road). 
  11. Height Clearance Certificate from Civil Aviation Authority (if in the surrounding of Airport or to achieve maximum height). 
  12. Utility Connection Approval: 
    1. Approval letter from Sui Northern Gas Pipeline (SNGPL) 
    2. Approval letter from Islamabad Electric Supply Company (IESCO) 
    3. Approval letter from Water Supply System 
  13. Approval letter for Fire Fighting System. 
  14. NOCs/ Environmental Approval from Pakistan Environmental Protection Agency (PakEPA). 
  15. Building Completion Certificate.

 