Commercial plaza construction cost in Pakistan 2021

Commercial plaza grey structure cost 5 marla frame structure rate in Pakistan

 

Commercial plaza construction cost

Previously, all articles on the cost by Team Overc’s were applicable on residential construction projects only, however, there was a very popular demand by our followers for commercial plaza construction cost frame structure. Since Team Overc’s already has the first-hand experience of various commercial projects successfully completed in Lahore & Islamabad, hence it is easy for us to guide our followers about the cost of commercial plazas built as a frame structure. However most of the methods of calculating cost might be the same as in our previous articles and videos, there is one significant change in this video where we have also mentioned quantities along with the per sqft costs.  Similar to previous residential costing videos, this costing video for the commercial plaza will also be only for grey structures.

Commercial plaza construction can be done by two methods which should be known before going towards the construction cost of the commercial plaza:

Labor contract

A contract in which the owner procures material and supervises labor on a self-help basis. A labor contractor is responsible for arranging required labor to carry out construction procedures. Construction cost is this case is all in hands of the owner himself. The final cost of construction will depend upon how well the owner has managed the construction process both in regards to material procurement and labor procurement. In this video, we will discuss the construction cost for this method.

Turnkey contract

This is a method or contract in which the owner hires a professional company on a lump sum or per square foot construction rate for a turnkey solution. The owner does not have to worry about the construction cost as the builder has agreed to provide him with all services within in predefined budget and cost. The owner only has to supervise if the builder is carrying out the work as per the agreement or not. At the end of this video, we will tell you how much a professional company charges for its services and how much per square foot you will have to pay extra than the cost that could have been if you build the commercial plaza yourself.

5 Marla commercial plaza construction cost (125 sq.yd)

Covered area TOTAL 4900 sq.ft including

  • Basement 1200 sqft
  • Ground floor 1200 sqft
  • first floor 1200 sqft
  • Second floor  1200 sqft
  • Mumtee 100 sqft

Item wise per square foot commercial plaza construction cost :

Bricks 125 Rs/sq.ft

Calculation:

125 Rs x 4900 sq.ft=612500 Rs

Brick price           =11.5 Rs per piece

Quantity              =612500/11.5 = 53260 bricks

Crush 131 Rs/sq.ft

Calculation:

131 Rs x 4900 sq.ft=641900 Rs

Crush price       =80 Rs per c.ft

Quantity         =641900/80 = 8024 c.ft

Cement 175 Rs/sq.ft

Calculation:

175 Rs x 4900 sq.ft=857500 Rs

Cement price       =500 Rs/50kg bag

Quantity              =857500/500 = 1715 bags

Steel 620 Rs/sq.ft

Calculation:

620 Rs x 4900 sq.ft=3038000 Rs

Steel price             =111 Rs/kg or 111000 Rs/ton

Quantity              =3038000/111 = 27370 kg or 27.37 tons

Sand 50 Rs/sq.ft

Calculation:

50 Rs x 4900 sq.ft=245000 Rs

Sand price         =30 Rs/c.ft

Quantity             =245000/30 = 8166 c.ft

Labor contractor 450 Rs/sq.ft

Calculation:

450 Rs x 4900 sq.ft = 2205000 Rs

Steel fixer 36 Rs/sq.ft

Calculation:

36 Rs x 4900 sq.ft = 176400 Rs

Plumbing contractor 18 Rs/sq.ft

Calculation:

18 Rs x 4900 sq.ft = 88200 Rs

Electric contractor 18 Rs/sq.ft

Calculation:

18 Rs x 4900 sq.ft = 88200 Rs

POINT TO BE NOTED:

The labor rate considered as 450 in this calculation includes each and everything related to labor & machinery such as masons, helpers,  mixing machines, vibrators, scaffolding, shuttering. Since this method of construction is a frame structure, shuttering has a very critical role. Best quality shuttering is done with steel plates of 4ftx8ft palai sheets. In this labor rate we have considered use of both steel plates and palai for shuttering of columns, slabs, basement retailing walls etc. Another critical labor is the steel fixer for which per ton labor rate has been considered at the rate of 6500  Rs. Similarly electrician and plumber rate includes complete work related to electrical and plumbing till grey structure i-e conduit in slabs and walls, hot and cold water pipes, drain pipes & main sewerage lines etc

Other items

 

Excavation 10 Rs/sq.ft

Calculation:

10 Rs x 4900 sq.ft= 49000 Rs

Water proofing 10 Rs/sq.ft

Calculation:

10 Rs x 4900 sq.ft= 49000 Rs

Waterproofing considered in this method is a simple chemical coating of Ultra of Sika any of the brand surface area rate of which is maximum up to 20 rs/sqft. For stronger waterproofing method of basement retaining walls PVC membrane sheets can be used however it will add up to the overall waterproofing cost because it is expensive.

Water stopper 5 Rs/sq.ft

Calculation:

5 Rs x 4900 sq.ft= 24500 Rs

Electricity items 35 Rs/sq.ft

Calculation:

35 Rs x 4900 sq.ft= 171500 Rs

Electric items include complete uPVC conduit (pipes) required in walls, slabs, underground etc. It also includes complete switch boards internal boxes fittings required for standard Chinese fittings. Main DB (Distribution boxes) are also included in these figures for ground and first floor. Electric conduit witnessed a sharp increase in prices in 2019/20 as compared to 2018.

Plumbing items 70 Rs/sq.ft

Calculation:

70 Rs x 4900 sq.ft= 343000 Rs

Plumbing items include complete PPRC pipes and its fittings such as elbows, bends, T’s etc required for water and gas connections. It also includes complete uPVC piping for sewerage and drain systems. It also includes a typical and standard 400 gallons plastic overhead water tank with GI (steel) pipes fitting. Plumbing conduit witnessed a sharp increase in prices in 2019/20 as compared to 2018.

 

Brick Tile 15 Rs/sq.ft

Calculation:

15 Rs x 4900 sq.ft= 73500 Rs

Brick tile is required during the process of water proofing and finishing the floor of roofs. Brick tile considered in this cost is up to 10 Rs/bricktile.

Guard Salary 16 Rs/sq.ft

Calculation:

16 Rs x 4900 sq.ft= 78400 Rs

Guard salary has been considered on basis of 15000 Rs/month for a tenure of 5 months maximum.

Gravel 20 Rs/sq.ft

Calculation:

20 Rs x 4900 sq.ft= 98000 Rs

Bitumen 5 Rs/sq.ft

Calculation:

5 Rs x 4900 sq.ft= 24500 Rs

Polythene sheet 4 Rs/sq.ft

Calculation:

4 Rs x 4900 sq.ft= 19600 Rs

Mud 4 Rs/sq.ft

Calculation:

4 Rs x 4900 sq.ft= 19600 Rs

Chips Aggregate 5 Rs/sq.ft

Calculation:

5 Rs x 4900 sq.ft= 24500 Rs

Taxes 6 Rs/sq.ft

Calculation:

6 Rs x 4900 sq.ft= 29400 Rs

Electricity bills 5 Rs/sq.ft

Calculation:

5 Rs x 4900 sq.ft= 24500 Rs

Water boring 5 Rs/sq.ft

Calculation:

5 Rs x 4900 sq.ft= 24500 Rs

Anti termite spray 7 Rs/sq.ft

Calculation:

7 Rs x 4900 sq.ft= 34300 Rs

Random expenditures 20 Rs/sq.ft

Calculation:

20 Rs x 4900 sq.ft= 98000 Rs

L et us see what will be the total cost of Grey structure for 5 marlas commercial plaza frame structure method:

Search

 

S# Item 2020 per sqft cost 2020 Total approximate cost
1 Bricks 125 612500
2 Crush 131 641900
3 Cement 175 857500
4 Steel 620 3038000
5 Sand 50 245000
6 Labor cont 450 2205000
7 Steel fixer 36 127400
8 Plumbing 18 88200
9 Electric 18 88200
10 Electric items 35 171500
11 Plumbing items 70 343000
12 Earthfill 0 0
13 Brick tile 15 73500
14 Guard Salary 14 68600
15 Gravel 20 98000
16 Excavation 10 49000
17 Bitumen 5 24500
18 Polythene sheet 4 19600
19 Mud 4 19600
20 Chips 5 24500
21 Taxes 6 29400
22 Electric bills 5 24500
23 Boring 5 24500
24 Anti termite 7 34300
25 Random 20 98000
26 Water proofing 10 49000
27 Water stopper 5 24500
  Total 1865 9138500

Disclaimer:

-Possible ±5% Variation is possible in the cost shown in the video
-Rates applicable on frame structures only in Lahore & Islamabad/Rawalpindi
-Skills required to achieve this cost:
-Past construction experience
-Quality & honest labor
-Labor management skills
-Quality, timely & cost-effective material procurement
-Factors such as construction inexperience, unusual
covered areas, frequent wear & tears, fraudulent labor
etc can affect this cost figure
-Hire a professional company which will add a figure of 200 Rs/sq.ft
minimum as margin.
-Basement grey structure will cost a minimum 2029 Rs/sq.ft

Residential costing Grey structure videos:

                                 

Share this post:

Tags


5 marla house construction cost calculator in Pakistan 2021 3 marla house construction cost calculator in Pakistan 2021 8 marla house construction cost calculator in Pakistan 2021 3 marla house construction cost in Lahore 2021 10 marla house construction cost 2021 7 marla house construction cost 2021 2.5 marla house construction cost in Pakistan 1 Kanal house construction cost in Lahore 2021

0 Comments

Leave us a Comment

About us

We believe that its very light version & Simple, Creative & Flexible Design with Standards

Main Office
Office 24, 2nd Floor, Bigcity Plaza,
Gulberg-III, Lahore
DHA Office
Ground Floor, Plaza B/148, Broadway
Commerial Phase, DHA Lahore
Phone: +(92) 322 8000 190
Office: +(92) 423 577 4098
Email: info@acco.com.pk

Working Hours

Our support team available to help you 24/7 a day

  1. Monday-Saturday: 9am to 6pm
  2. Sunday: Closed
  3. Help Desk: Open 24/7